This project through the US Army Corps of Engineers saw over 22K CY of specialized concrete placed. The work will protect the city of Jamestown and surrounding communities and at time required 7 day/week production and at time requiring 150CY/hr +
Portable Operation set up to deliver over 25K CY of concrete in phase I of the Applied Digital Corporation Artificial Intelligence project - which is the largest AI project being built in the US.
Paving project in South Fargo 2024. Coordinating day in and day out schedules coupled with the high demand of over 140 CY/hour for a project like this is attainable as we run 2 - ready mix plants in the Fargo/Moorhead area. Not interrupting service is our priority.
Copyright © 2024 KOST MATERIALS - All Rights Reserved.
Powered by GoDaddy Website Builder